Progress of construction at the site: key stages and results
| News
Kazakh Construction Group LLP continues construction work at the site of the integrated gas treatment plant (IGTP).
Currently, work is being carried out in the following areas:
- Earthworks (development, backfilling, compaction) — 77% complete;
- Installation of process equipment — 38% complete;
- Concrete works (installation of foundations, bottoms, structures, etc.) — 64% complete.
Work on Title No. 8 and other areas
Preparatory activities for the installation of process equipment are underway at Title No. 8. The following types of work are being carried out at more than 40 title areas:
- backfilling and soil compaction;
- laying and testing of pipelines;
- installation of wells;
- waterproofing of walls and foundations;
- concrete works.
Testing of tanks with filling with technical water, as well as welding work, are being carried out.
Kazakh Construction Group LLP continues the consistent implementation of the project in accordance with the approved schedule, ensuring the smooth execution of all stages of construction.