Progress of construction on the Kashagan gas processing plant project
Skip to main content

News and Events

Progress of construction on the Kashagan gas processing plant project

| News
Progress of construction on the Kashagan gas processing plant project

“Kazakh Construction Group” LLC continues active implementation of construction works within the framework of the Kashagan gas processing plant (GPP) project, located at the Yeskene field, Atyrau region.

As for the reporting date, the following key types of work are performed:

• Conducting hydraulic testing of a 1000 m³ tank, preparing for hydraulic testing of a 5000 m³ tank.
• Installation and welding work on tanks.
• Painting of metal structures.
• Digging trenches and installing pipelines.
• Installation of metal structures of the administrative and amenity building.
• Installation of water supply/sewage pipelines.
• Installation of metal structures and installation of equipment.
• Installation of formwork and concrete.
• Reinforcement of structures in the sulfur pit area.
• Backfilling and other earthworks at construction sites.
• Installation of metal structures on overpasses.
• Preparation and painting of metal structures for all objects.
• Concrete work (foundations, bottoms, structures).
• Welding work and installation of the tank farm.

Progress in key areas (as of the previous reporting week):

Type of work Progress (%)
• Earthworks (development, backfilling, compaction) - 39.4%
• Installation of process equipment - 42.5%
• Concrete works (foundations, bottoms, structures) - 69.8%

All construction processes are carried out in strict accordance with the approved schedule, in compliance with high quality standards and safety requirements.

KAZAKH
CONSTRUCTION GROUP

Actual address:
Republic of Kazakhstan, Atyrau city, 117/1 Kulmanov Street

Legal address:
Republic of Kazakhstan, Astana city, Yesil district, Dinmukhamed Kunayev Street, building 12/1, unit 16

Phone: +7 771 076 64 50
Email: dcc_atyrau@kcg.company

ISO 9001 | ISO 14001 | ISO 45001