«Kazakh Construction Group» LLP continues construction work at the Kashagan gas treatment plant.
Over the past week, the following work has been successfully completed:
Installation of process equipment — the waste heat boiler of the afterburner (E-07013, weight 76 tons) on title No. 7 has been completed.
In parallel, excavation work is underway, including concreting and backfilling.
Backfilling is the final stage of excavation work and marks the transition to the main stage of installation work.
Alco, concrete cubes selected from title No. 49 on May 23 were also successfully tested.
The results of testing 28-day samples showed high strength indicators.
The average strength of B25 (M350) concrete with a standard of 32.11 MPa was 36.6 MPa, which corresponds to 114% of the standard.
This confirms the high quality of the concrete mix and compliance with all technological requirements for the production and laying of concrete.