Currently, construction and installation works are actively carried out at the Kashagan gas treatment plant construction site
| News
Pile driving work is 100% completed. Earthworks are 58.1% completed. Concrete work for the main facilities is 59.2% completed.
Metalwork has begun and is currently 11.6% completed. Work on providing external water supply and sewerage systems is 99% completed.
Mechanical equipment is also being installed and is 24.67% completed.